Our pass rate is high to 98.9% and the similarity percentage between our ccnp tshoot 300 135 dumps study guide and real exam is 90% based on our seven-year educating experience. Do you want achievements in the Cisco ccnp tshoot 300 135 exam in just one try? I am currently studying for the Cisco 300 135 dumps exam. Latest Cisco 300 135 tshoot Test exam practice questions and answers, Try Cisco ccnp tshoot 300 135 dumps pdf Brain Dumps First.
2026 New 300-135 Exam Dumps with PDF and VCE Free: https://www.2passeasy.com/dumps/300-135/
Q1. - (Topic 13)
The implementations group has been using the test bed to do a ‘proof-of-concept' that requires both Client 1 and Client 2 to access the WEB Server at 209.65.200.241. After several changes to the network addressing, routing scheme, DHCP services,
NTP services, layer 2 connectivity, FHRP services, and device security, a trouble ticket has been opened indicating that Client 1 cannot ping the 209.65.200.241 address.
Use the supported commands to isolated the cause of this fault and answer the following questions.
The fault condition is related to which technology?
A. NTP
B. IP DHCP Server
C. IPv4 OSPF Routing
D. IPv4 EIGRP Routing
E. IPv4 Route Redistribution
F. IPv6 RIP Routing
G. IPv6 OSPF Routing
H. IPv4 and IPv6 Interoperability
I. IPv4 layer 3 security
Answer: E
Explanation:
On R4, in the redistribution of EIGRP routing protocol, we need to change name of route-map to resolve the issue. It references route-map OSPF_to_EIGRP but the actual route map is called OSPF->EIGRP.
Q2. - (Topic 1)
Which three features are benefits of using GRE tunnels in conjunction with IPsec for building siteto-site VPNs? (Choose three.)
A. allows dynamic routing over the tunnel
B. supports multi-protocol (non-IP) traffic over the tunnel
C. reduces IPsec headers overhead since tunnel mode is used
D. simplifies the ACL used in the crypto map
E. uses Virtual Tunnel Interface (VTI) to simplify the IPsec VPN configuration
Answer: A,B,D
Q3. - (Topic 2)
A customer network engineer has made configuration changes that have resulted in some loss of connectivity. You have been called in to evaluate a switch network and suggest resolutions to the problems.
Refer to the topology.
SW1 Switch Management IP address is not pingable from SW4. What could be the issue?
A. Management VLAN not allowed in the trunk links between SW1 and SW4
B. Management VLAN not allowed in the trunk links between SW1 and SW2
C. Management VLAN not allowed in the trunk link between SW2 and SW4
D. Management VLAN ip address on SW4 is configured in wrong subnet
E. Management VLAN interface is shutdown on SW4
Answer: D
Explanation:
In the network, VLAN 300 is called the Management VLAN. Based on the configurations shown below, SW1 has VLAN 300 configured with the IP address of 192.168.10.1/24, while on SW4 VLAN 300 has an IP address of 192.168.100.4/24, which is not in the same subnet.
Q4. - (Topic 16)
The implementations group has been using the test bed to do a ‘proof-of-concept'. After several changes to the network addressing, routing schemes, a trouble ticket has been opened indicating that the loopback address on R1 (2026::111:1) is not able to ping the loopback address on DSW2(2026::102:1).
Use the supported commands to isolated the cause of this fault and answer the following questions.
On which device is the fault condition located?
A. R1
B. R2
C. R3
D. R4
E. DSW1
F. DSW2
G. ASW1
H. ASW2
Answer: B
Explanation:
R2 is missing the needed IPV6 OSPF for interface s0/0/0.23
Topic 17, Ticket 12 : HSRP Issue
Topology Overview (Actual Troubleshooting lab design is for below network design)
. Client Should have IP 10.2.1.3
. EIGRP 100 is running between switch DSW1 & DSW2
. OSPF (Process ID 1) is running between R1, R2, R3, R4
. Network of OSPF is redistributed in EIGRP
. BGP 65001 is configured on R1 with Webserver cloud AS 65002
. HSRP is running between DSW1 & DSW2 Switches
The company has created the test bed shown in the layer 2 and layer 3 topology exhibits.
This network consists of four routers, two layer 3 switches and two layer 2 switches.
In the IPv4 layer 3 topology, R1, R2, R3, and R4 are running OSPF with an OSPF process number 1.
DSW1, DSW2 and R4 are running EIGRP with an AS of 10. Redistribution is enabled where necessary.
R1 is running a BGP AS with a number of 65001. This AS has an eBGP connection to AS 65002 in the ISP's network. Because the company's address space is in the private range.
R1 is also providing NAT translations between the inside (10.1.0.0/16 & 10.2.0.0/16) networks and outside (209.65.0.0/24) network.
ASW1 and ASW2 are layer 2 switches.
NTP is enabled on all devices with 209.65.200.226 serving as the master clock source.
The client workstations receive their IP address and default gateway via R4's DHCP server.
The default gateway address of 10.2.1.254 is the IP address of HSRP group 10 which is running on DSW1 and DSW2.
In the IPv6 layer 3 topology R1, R2, and R3 are running OSPFv3 with an OSPF process number 6.
DSW1, DSW2 and R4 are running RIPng process name RIP_ZONE.
The two IPv6 routing domains, OSPF 6 and RIPng are connected via GRE tunnel running over the underlying IPv4 OSPF domain. Redistrution is enabled where necessary.
Recently the implementation group has been using the test bed to do a ‘proof-of-concept' on several implementations. This involved changing the configuration on one or more of the
devices. You will be presented with a series of trouble tickets related to issues introduced during these configurations.
Note: Although trouble tickets have many similar fault indications, each ticket has its own issue and solution.
Each ticket has 3 sub questions that need to be answered & topology remains same.
Question-1 Fault is found on which device,
Question-2 Fault condition is related to,
Question-3 What exact problem is seen & what needs to be done for solution
Solution
Steps need to follow as below:-
. Since the problem is raised that DSW1 will not become active router for HSRP group 10
. we will check for the HSRP configuration…
. From snapshot we see that the track command given needs to be changed under active VLAN10 router
. Change Required: On DSW1, related to HSRP, under vlan 10 change the given track 1 command to instead use the track 10 command.
Q5. - (Topic 13)
The implementations group has been using the test bed to do a ‘proof-of-concept' that requires both Client 1 and Client 2 to access the WEB Server at 209.65.200.241. After several changes to the network addressing, routing scheme, DHCP services, NTP services, layer 2 connectivity, FHRP services, and device security, a trouble ticket has been opened indicating that Client 1 cannot ping the 209.65.200.241 address.
Use the supported commands to isolated the cause of this fault and answer the following questions.
Which is the solution to the fault condition?
A. Under the EIGRP process, delete the redistribute ospf 1 route-map OSPF_ to_ EIGRP command and enter the redistribute ospf 1 route-map OSPF - > EIGRP command.
B. Under the EIGRP process, delete the redistribute ospf 1 route-map OSPF_ to_ EIGRP command and enter the redistribute ospf 6 metric route-map OSPF - > EIGRP command.
C. Under the OSPF process, delete the redistribute eigrp10 subnets route-map EIGPR ->OSPF command and enter the redistribute eigrp10 subnets route-map OSPF - > EIGRP command.
D. Under the OSPF process, delete the redistribute eigrp10 subnets route-map EIGPR ->OSPF command and enter the redistribute eigrp10 subnets route-map EIGPR - > OSPF command.
E. Under the EIGRP process, delete the redistribute ospf 1 route-map OSPF _to_ EIGRP command and enter redistribute ospf 1 metric 100000 100 100 1 15000 route_ map OSPF _to _EIGRP command
Answer: A
Explanation:
On R4, in the redistribution of EIGRP routing protocol, we need to change name of route-map to resolve the issue. It references route-map OSPF_to_EIGRP but the actual route map is called OSPF->EIGRP.
Topic 14, Ticket 9 : EIGRP AS number
Topology Overview (Actual Troubleshooting lab design is for below network design)
. Client Should have IP 10.2.1.3
. EIGRP 100 is running between switch DSW1 & DSW2
. OSPF (Process ID 1) is running between R1, R2, R3, R4
. Network of OSPF is redistributed in EIGRP
. BGP 65001 is configured on R1 with Webserver cloud AS 65002
. HSRP is running between DSW1 & DSW2 Switches
The company has created the test bed shown in the layer 2 and layer 3 topology exhibits.
This network consists of four routers, two layer 3 switches and two layer 2 switches.
In the IPv4 layer 3 topology, R1, R2, R3, and R4 are running OSPF with an OSPF process number 1.
DSW1, DSW2 and R4 are running EIGRP with an AS of 10. Redistribution is enabled where necessary.
R1 is running a BGP AS with a number of 65001. This AS has an eBGP connection to AS 65002 in the ISP's network. Because the company's address space is in the private range.
R1 is also providing NAT translations between the inside (10.1.0.0/16 & 10.2.0.0/16) networks and outside (209.65.0.0/24) network.
ASW1 and ASW2 are layer 2 switches.
NTP is enabled on all devices with 209.65.200.226 serving as the master clock source.
The client workstations receive their IP address and default gateway via R4's DHCP server.
The default gateway address of 10.2.1.254 is the IP address of HSRP group 10 which is running on DSW1 and DSW2.
In the IPv6 layer 3 topology R1, R2, and R3 are running OSPFv3 with an OSPF process number 6.
DSW1, DSW2 and R4 are running RIPng process name RIP_ZONE.
The two IPv6 routing domains, OSPF 6 and RIPng are connected via GRE tunnel running over the underlying IPv4 OSPF domain. Redistrution is enabled where necessary.
Recently the implementation group has been using the test bed to do a ‘proof-of-concept' on several implementations. This involved changing the configuration on one or more of the devices. You will be presented with a series of trouble tickets related to issues introduced during these configurations.
Note: Although trouble tickets have many similar fault indications, each ticket has its own issue and solution.
Each ticket has 3 sub questions that need to be answered & topology remains same.
Question-1 Fault is found on which device,
Question-2 Fault condition is related to,
Question-3 What exact problem is seen & what needs to be done for solution
Client is unable to ping IP 209.65.200.241
Solution
Steps need to follow as below:-
. When we check on client 1 & Client 2 desktop we are not receiving DHCP address from R4
ipconfig ----- Client will be receiving IP address 10.2.1.3
. From Client PC we can ping 10.2.1.254
. But IP 10.2.1.3 is not able to ping from R4, R3, R2, R1 .
. This clearly shows problem at R4 Kindly check routes in EIGRP there are no routes of eigrp.
. Check the neighborship of EIGRP on R4; there are no neighbor seen from DSW1 & DSW2 check the running config of EIGRP protocol it shows EIGRP AS 1 process…. Now check on DSW1 & DSW2
On DSW1 only one Eigrp neighbour is there with DSW2 but its not with R4…
. From above snapshot & since R4 has EIGRP AS number 1 due to which neighbour is not happening.
. Change required: On R4, IPV4 EIGRP Routing, need to change the EIGRP AS number from 1 to 10 since DSW1 & DSW2 is configured to be in EIGRP AS number 10.
Q6. - (Topic 17)
The implementations group has been using the test bed to do a ‘proof-of-concept' that requires both Client 1 and Client 2 to access the WEB Server at 209.65.200.241. After several changes to the network addressing, routing schemes, DHCP services, NTP services, layer 2 connectivity, FHRP services, and device security, a trouble ticket has been opened DSW1 will not become the active router for HSRP group 10.
Use the supported commands to isolated the cause of this fault and answer the following questions.
What is the solution to the fault condition?
A. Under the interface vlan 10 configuration enter standby 10 preempt command.
B. Under the track 1 object configuration delete the threshold metric up 1 down 2 command and enter the threshold metric up 61 down 62 command.
C. Under the track 10 object configuration delete the threshold metric up 61 down 62 command and enter the threshold metric up 1 down 2 command.
D. Under the interface vlan 10 configuration delete the standby 10 track1 decrement 60 command and enter the standby 10 track 10 decrement 60 command.
Answer: D
Explanation:
On DSW1, related to HSRP, under VLAN 10 change the given track 1 command to instead use the track 10 command.
Q7. - (Topic 5)
Scenario: A customer network engineer has edited their OSPF network configuration and now your customer is experiencing network issues. They have contacted you to resolve the issues and return the network to full functionality.
The 6.6.0.0 subnets are not reachable from R4. how should the problem be resolved?
A. Edit access-list 46 in R6 to permit all the 6.6.0.0 subnets
B. Apply access-list 46 in R6 to a different interface
C. Apply access-list 1 as a distribute-list out under router ospf 100 in R4
D. Remove distribute-list 64 out on R6 E. Remove distribute-list 1 in ethernet 0/1 in R4
F. Remove distribute-list 1 in ethernet 0/0 in R4
Answer: D
Explanation:
Here we see from the running configuration of R6 that distribute list 64 is being used in the outbound direction to all OSPF neighbors.
However, no packets will match the 6.6.0.0 in this access list because the first line blocks all 6.0.0.0 networks, and since the 6.6.0.0 networks will also match the first line of this ACL, these OSPF networks will not be advertised because they are first denied in the first line of the ACL.
Q8. - (Topic 4)
Scenario:
You have been asked by your customer to help resolve issues in their routed network. Their network engineer has deployed HSRP. On closer inspection HSRP doesn't appear to be operating properly and it appears there are other network problems as well. You are to provide solutions to all the network problems.
You have received notification from network monitoring system that link between R1 and R5 is down and you noticed that the active router for HSRP group 1 has not failed over to the standby router for group 1. You are required to troubleshoot and identify the issue.
A. There is an HSRP group track command misconfiguration
B. There is an HSRP group priority misconfiguration
C. There is an HSRP authentication misconfiguration
D. There is an HSRP group number mismatch
E. This is not an HSRP issue; this is routing issue.
Answer: A
Explanation:
When looking at the HSRP configuration of R1, we see that tracking has been enabled, but that it is not tracking the link to R5, only the link to R2:
R1 should be tracking the Eth 0/1 link, not 0/0 to achieve the desired affect/
Q9. - (Topic 15)
The implementations group has been using the test bed to do a ‘proof-of-concept' that requires both Client 1 and Client 2 to access the WEB Server at 209.65.200.241. After several changes to the network addressing, routing scheme, DHCP services, NTP services, layer 2 connectivity, FHRP services, and device security, a trouble ticket has been opened indicating that Client 1 cannot ping the 209.65.200.241 address.
Use the supported commands to isolated the cause of this fault and answer the following questions.
The fault condition is related to which technology?
A. NTP
B. IP DHCP Helper
C. IPv4 EIGRP Routing
D. IPv6 RIP Routing
E. IPv4 layer 3 security
F. Switch-to-Switch Connectivity
G. Loop Prevention
H. Access Vlans
I. Port Security
J. VLAN ACL / Port ACL
K. Switch Virtual Interface
Answer: J
Explanation:
On DSW1, VALN ACL, Need to delete the VLAN access-map test1 whose action is to drop access-list 10; specifically 10.2.1.3
Q10. - (Topic 14)
The implementations group has been using the test bed to do a ‘proof-of-concept' that requires both Client 1 and Client 2 to access the WEB Server at 209.65.200.241. After several changes to the network addressing, routing scheme, DHCP services, NTP services, layer 2 connectivity, FHRP services, and device security, a trouble ticket has been opened indicating that Client 1 cannot ping the 209.65.200.241 address.
Use the supported commands to isolated the cause of this fault and answer the following questions.
The fault condition is related to which technology?
A. NTP
B. IP DHCP Server
C. IPv4 OSPF Routing
D. IPv4 EIGRP Routing
E. IPv4 Route Redistribution
F. IPv6 RIP Routing
G. IPv6 OSPF Routing
H. IPv4 and IPv6 Interoperability
I. IPv4 layer 3 security
Answer: D
Explanation:
On R4, IPV4 EIGRP Routing, need to change the EIGRP AS number from 1 to 10 since DSW1 & DSW2 is configured to be in EIGRP AS number 10.
Topic 15, Ticket 10 : VLAN Access Map
Topology Overview (Actual Troubleshooting lab design is for below network design)
. Client Should have IP 10.2.1.3
. EIGRP 100 is running between switch DSW1 & DSW2
. OSPF (Process ID 1) is running between R1, R2, R3, R4
. Network of OSPF is redistributed in EIGRP
. BGP 65001 is configured on R1 with Webserver cloud AS 65002
. HSRP is running between DSW1 & DSW2 Switches
The company has created the test bed shown in the layer 2 and layer 3 topology exhibits.
This network consists of four routers, two layer 3 switches and two layer 2 switches.
In the IPv4 layer 3 topology, R1, R2, R3, and R4 are running OSPF with an OSPF process number 1.
DSW1, DSW2 and R4 are running EIGRP with an AS of 10. Redistribution is enabled where necessary.
R1 is running a BGP AS with a number of 65001. This AS has an eBGP connection to AS 65002 in the ISP's network. Because the company's address space is in the private range.
R1 is also providing NAT translations between the inside (10.1.0.0/16 & 10.2.0.0/16) networks and outside (209.65.0.0/24) network.
ASW1 and ASW2 are layer 2 switches.
NTP is enabled on all devices with 209.65.200.226 serving as the master clock source.
The client workstations receive their IP address and default gateway via R4's DHCP server.
The default gateway address of 10.2.1.254 is the IP address of HSRP group 10 which is running on DSW1 and DSW2.
In the IPv6 layer 3 topology R1, R2, and R3 are running OSPFv3 with an OSPF process number 6.
DSW1, DSW2 and R4 are running RIPng process name RIP_ZONE.
The two IPv6 routing domains, OSPF 6 and RIPng are connected via GRE tunnel running over the underlying IPv4 OSPF domain. Redistrution is enabled where necessary.
Recently the implementation group has been using the test bed to do a ‘proof-of-concept' on several implementations. This involved changing the configuration on one or more of the devices. You will be presented with a series of trouble tickets related to issues introduced during these configurations.
Note: Although trouble tickets have many similar fault indications, each ticket has its own issue and solution.
Each ticket has 3 sub questions that need to be answered & topology remains same.
Question-1 Fault is found on which device,
Question-2 Fault condition is related to,
Question-3 What exact problem is seen & what needs to be done for solution
Client 1 is unable to ping IP 209.65.200.241
Solution
Steps need to follow as below:-
. When we check on client 1 & Client 2 desktop we are not receiving DHCP address from R4
ipconfig ----- Client will be receiving IP address 10.2.1.3
. From Client PC we can ping 10.2.1.254….
. But IP 10.2.1.3 is not able to ping from R4, R3, R2, R1
. Change required: On DSW1, VALN ACL, Need to delete the VLAN access-map test1 whose action is to drop access-list 10; specifically 10.2.1.3