It is more faster and easier to pass the PRINCE2-Exams prince2 foundation sample exam questions and answers pdf exam by using Refined PRINCE2-Exams PRINCE2 Foundation exam questuins and answers. Immediate access to the Avant-garde prince2 foundation london Exam and find the same core area prince2 foundation exam questions and answers free questions with professionally verified answers, then PASS your exam with a high score now.
2026 New PRINCE2-Foundation Exam Dumps with PDF and VCE Free: https://www.2passeasy.com/dumps/PRINCE2-Foundation/
Q1. - (Topic 2)
Which is a true statement about time-driven controls?
A. Time-driven controls are used for monitoring the progress of Work Packages and management stages
B. Time-driven controls take place when specific events happen
C. Time-driven controls are produced at the end of a stage
D. An Exception Report is a time-driven control
Answer: A
Q2. - (Topic 1)
Which two roles are linked by the Managing Product Delivery process?
A. Corporate or programme management and Project Board
B. Project Board and Project Manager
C. Project Manager and Team Manager
D. Team Manager and external supplier
Answer: C
Q3. - (Topic 2)
Which is a true statement about acceptance criteria?
A. Acceptance criteria are used to produce the customer's quality expectations
B. Acceptance criteria are less specific and precise than customer's quality expectations
C. Once agreed, acceptance criteria CANNOT be changed
D. Acceptance criteria should be agreed between the customer and the supplier
Answer: D
Q4. - (Topic 2)
Which is shown in a product breakdown structure?
A. Management stages, major products and control points
B. In which order the products should be created
C. The major products that are to be developed in a plan
D. What resources are required to develop the products
Answer: C
Q5. - (Topic 1)
What is an off-specification?
A. A new requirement
B. A quality tolerance
C. A type of issue
D. A major risk
Answer: C
Q6. - (Topic 2)
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.
A. change budget
B. project budget
C. project's cost tolerance
D. project's risk tolerance
Answer: B
Q7. - (Topic 1)
What takes place during the Closing a Project process?
A. The post-project benefits reviews are performed
B. Ownership of the project's products is transferred to the customer
C. An End Stage Report is prepared for the final stage
D. The project closure notification is reviewed and approved
Answer: B
Q8. - (Topic 2)
Who carries out audits that are independent of the project?
A. Quality assurance
B. Project Assurance
C. Project Support
D. Project Manager
Answer: A
Q9. - (Topic 1)
Which is a purpose of the Directing a Project process?
A. Create and authorize the project mandate
B. Ensure that work on products allocated to the team is authorized and agreed
C. Control the day-to-day running of the project
D. Delegate day-to-day management of the project to the Project Manager
Answer: D
Q10. - (Topic 2)
Which is part of quality control?
A. Undertake quality reviews
B. Write Product Descriptions
C. Provide assurance that the project is being conducted properly
D. Document the customer's quality expectations
Answer: A