It is more faster and easier to pass the PMI CAPM exam by using Real PMI Certified Associate in Project Management (PMI-100) questuins and answers. Immediate access to the Refresh CAPM Exam and find the same core area CAPM questions with professionally verified answers, then PASS your exam with a high score now.
Also have CAPM free dumps questions for you:
NEW QUESTION 1
Which cost estimate technique includes contingencies to account for cost uncertainty?
- A. Vendor bid analysis
- B. Three-point estimates
- C. Parametric estimating
- D. Reserve analysis
Answer: D
NEW QUESTION 2
Who selects the appropriate processes for a project?
- A. Project stakeholders
- B. Project sponsor and project stakeholder
- C. Project manager and project team
- D. Project manager and project sponsor
Answer: C
NEW QUESTION 3
The milestone list is an input to which process from the Planning Process Group?
- A. Define Activities
- B. Estimate Activity Durations
- C. Estimate Activity Resources
- D. Sequence Activities
Answer: D
NEW QUESTION 4
Which of the following is a tool or technique used in the Acquire Project Team process?
- A. Networking
- B. Training
- C. Negotiation
- D. Issue log
Answer: C
NEW QUESTION 5
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
- A. Expert judgment.
- B. Analytical techniques.
- C. Earned value management.
- D. Group decision-making technique
Answer: B
NEW QUESTION 6
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?
- A. US$S000
- B. US$9500
- C. US$10,000
- D. US$12,500
Answer: D
NEW QUESTION 7
What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed?
- A. Organizational process assets
- B. Enterprise environmental factors
- C. Project management processes
- D. Project scope management plan
Answer: A
NEW QUESTION 8
Resource calendars are included in the:
- A. staffing management plan.
- B. work breakdown structure (WBS).
- C. project communications plan.
- D. project charte
Answer: A
NEW QUESTION 9
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?
- A. Requirements documentation
- B. Requirements traceability matrix
- C. Project management plan updates
- D. Project documents updates
Answer: B
NEW QUESTION 10
In which process is a project manager identified and given the authority to apply resources to project activities?
- A. Acquire Project Team
- B. Develop Project Management Plan
- C. Manage Project Execution
- D. Develop Project Charter
Answer: D
NEW QUESTION 11
Identify Risks is part of which Process Group?
- A. Planning
- B. Executing
- C. Closing
- D. Initiating
Answer: A
NEW QUESTION 12
During which process group is the quality policy determined?
- A. Initiating
- B. Executing
- C. Planning
- D. Controlling
Answer: C
NEW QUESTION 13
Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?
- A. Information management systems
- B. Work performance reports
- C. Stakeholder analysis
- D. Data gathering and representation
Answer: A
NEW QUESTION 14
Which technique is used in Perform Quantitative Risk Analysis?
- A. Sensitivity analysis
- B. Probability and impact matrix
- C. Risk data quality assessment
- D. Risk categorization
Answer: A
NEW QUESTION 15
Which item is a formal proposal to modify any document, deliverable, or baseline?
- A. Change request
- B. Requirements documentation
- C. Scope baseline
- D. Risk urgency assessment
Answer: A
NEW QUESTION 16
Which of the following is an input to Control Scope?
- A. Project schedule
- B. Organizational process assets updates
- C. Project document updates
- D. Work performance information
Answer: D
NEW QUESTION 17
The process improvement plan details the steps for analyzing processes to identify activities which enhance their:
- A. quality.
- B. value.
- C. technical performance.
- D. statu
Answer: B
NEW QUESTION 18
Which is an example of Administer Procurements?
- A. Negotiating the contract
- B. Authorizing contractor work
- C. Developing the statement of work
- D. Establishing evaluation criteria
Answer: B
NEW QUESTION 19
During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?
- A. Monitor and Control Project Work
- B. Perform Quality Assurance
- C. Close Project or Phase
- D. Control Scope
Answer: C
NEW QUESTION 20
Information collected on the status of project activities being performed to accomplish the project work is known as what?
- A. Project management information system
- B. Work performance information
- C. Work breakdown structure
- D. Variance analysis
Answer: B
NEW QUESTION 21
Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
- A. Perform Qualitative Risk Analysis
- B. Perform Quantitative Risk Analysis
- C. Plan Risk Management
- D. Plan Risk Responses
Answer: A
NEW QUESTION 22
Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?
- A. Facilitation techniques
- B. Expert judgment
- C. Analytical techniques
- D. Variance analysis
Answer: C
NEW QUESTION 23
Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?
- A. Portfolio
- B. Project
- C. Program
- D. Operations
Answer: D
NEW QUESTION 24
A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:
- A. To the project management plan.
- B. To the risk register.
- C. In the scope verification processes.
- D. And their impact to the project in terms of time, cost, and ris
Answer: D
NEW QUESTION 25
A tool or technique in Perform Quality Control that a project manager would use is:
- A. quality audits.
- B. process analysis.
- C. benchmarking.
- D. inspection.
Answer: D
NEW QUESTION 26
......