Your success in CompTIA PK0-004 is our sole target and we develop all our PK0-004 braindumps in a way that facilitates the attainment of this target. Not only is our PK0-004 study material the best you can find, it is also the most detailed and the most updated. PK0-004 Practice Exams for CompTIA Project+ PK0-004 are written to the highest standards of technical accuracy.


2026 New PK0-004 Exam Dumps with PDF and VCE Free: https://www.2passeasy.com/dumps/PK0-004/

Q1. An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.

Which of the following actions should the project manager take?

A. Submit a new change request.

B. Initiate the regression plan.

C. Add remediation to the schedule.

D. Accept the new power output.

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p.294

Q2. During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor’s tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months.

Which of the following should have occurred to prevent this issue?

A. During the planning phase, the project manager should have recognized the relationship between the vendor’s and project team’s tasks and adjusted the schedule for the project team to begin activities two months later.

B. The project manager should have crashed the schedule for the vendor to keep it at the same work pace as the rest of the project team.

C. During the project team’s regular status meeting with the vendor, the project team should have informed the vendor that the team was ahead of schedule and to speed up their work.

D. During the project team’s regular status meeting with the vendor, the vendor should have informed the project team that it required another two months, and to slow down.

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 170

Q3. A project manager noticed the development team supporting a project does not have sufficient skills to complete the development phase. The project manager has discussed this issue with the functional manager and agreed to continue with the development phase due to time restrictions.

Which of the following strategies is the project manager applying?

A. Accepting

B. Mitigating

C. Avoiding

D. Transferring

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 238

Q4. Which of the following describes how a project is related to a program?

A. A program is a combination of multiple projects.

B. A program contains an element of the project.

C. A program is a part of a project.

D. A program uses half of the project’s budget.

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p.72

Q5. During the execution phase of a project, a project task has run longer than anticipated.

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?

A. 12 days

B. 14 days

C. 16 days

D. 19 days

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p.169

Q6. Which of the following is a schedule that illustrates the duration of an activity?

A. Process diagram

B. Ishikawa diagram

C. Gantt chart

D. Pareto chart

Answer: C

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 168

Q7. Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.

The project manager should:

A. follow the change process flow and notify the legal department after the change is implemented.

B. extend a formal invitation to the legal department representative to join the CCB.

C. hold a separate meeting with the legal department representative and ask for approval.

D. notify the legal department representative in the event of an upcoming audit.

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 294

Q8. The project manager has noticed a vendor is not performing in accordance with the SLA.

Which of the following items should the project manager use to highlight the vendor’s areas of poor performance?

A. Balanced score card

B. WBS

C. Post-project evaluation

D. PERT

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 332

Q9. Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?

A. EAC

B. BAC

C. TCPI

D. ETC

Answer: D

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 232

Q10. A customer will have ongoing changes to project requirements.

Which of the following is the BEST project management methodology for this requirement?

A. Waterfall

B. Agile

C. PRINCE2

D. Bottom-up

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 310