Cause all that matters here is passing the Oracle 1Z0-567 exam. Cause all that you need is a high score of 1Z0-567 Primavera P6 Enterprise Project Portfolio Management 8 Essentials exam. The only one thing you need to do is downloading Examcollection 1Z0-567 exam study guides now. We will not let you down with our money-back guarantee.

Also have 1Z0-567 free dumps questions for you:

NEW QUESTION 1
You are an implementation consultant working at a company where project schedules have been managed primarily with Microsoft Project, on individual desktops. The "projects" theoretically have been multiple-year projects. Your scope of work includes migrating project data from legacy project plans and setting up project planning standards. As you look into the current Microsoft Project plans, it becomes clear that the projects are not really multi-year projects. The plans have been managed by creating "new" projects within the old projects by skipping a few lines in what has become more of a program history.
What approach would you recommend to retain the legacy data (which is a mandated requirement in the new Primavera system), while moving forward with a "one project, one plan" process?

  • A. Import all MS Project plans directly into the P6 production database "as is."
  • B. Import MS Project plans but break out current in-flight work into separate projects.
  • C. Create new projects only for in flight work identified in MS Project plans.
  • D. Retire legacy project plans and start with new project planning standards.

Answer: B

NEW QUESTION 2
Yon are working with a customer that has had a legacy Primavera release installed and running in their environment for four years, the CIO tells you that the current EPS does not show the data the way he would like to view it, and, therefore, he would like to restructure the entire EPS.
Before proceeding, what four options would you present to the CIO so that organizational Impacts are eliminated?

  • A. Modify the EPS.
  • B. Identify the reporting requirements.
  • C. Restructure the OBS.
  • D. Add project codes
  • E. Modify global filters.
  • F. Create user-specific filters.
  • G. Modify Group and Sort.

Answer: ABDE

Explanation:
E: Global filters are made available to anyone working in the database,

NEW QUESTION 3
You are a project manager addressing risk responses in your Risk Register. As you created your Risk Register, you also created multiple mitigating/response plans for each risk. Identify the functionality that will indicate which response plan is primary.

  • A. Response plan marked Active
  • B. Response plan with the closest start date
  • C. Response plan with lowest cost
  • D. Response plan marked highest priority

Answer: A

Explanation:
Response Plan row: Create one or more response plans while you are in the planning phase and indicate the response type. When you have analyzed your response options, choose one response plan by selecting the Active option next to the appropriate response plan.
In the example below, two response plans have been created for the Concrete supply constrained risk. The first plan is to accept the risk and take no action; the second plan is to reduce the impact of the risk by contracting with alternative suppliers. You can see this second plan was selected as the plan of choice.
1Z0-567 dumps exhibit
Note:
* A risk register and risk scoring matrix provide a system for monitoring and tracking risks.
* Rather than having a single response, you can create multiple responses to a risk.
* Once you have established your risks, you can view the Probability and Impact Diagram, which shows how the risks are coded. Several pre-defined PID matrices have been provided from which we can choose.
1Z0-567 dumps exhibit
Reference: Oracle Primavera P6, Working with Risk Response Plans

NEW QUESTION 4
Identify the best definition of the EPS.

  • A. The hierarchical definition of project budgets and actual costs.
  • B. The hierarchical definition of reporting structures.
  • C. The hierarchical structure of the security for projects.
  • D. The hierarchical structure of the database of projects.

Answer: D

Explanation:
Enterprise Project Structure (EPS)
The EPS is the outsider's view of your company, showing your lines of business. The EPS is laid out in a tree structure.
The EPS is used to organize and manage the projects in your organization.
Your database of projects is arranged in a hierarchy called the enterprise project structure (EPS).

NEW QUESTION 5
Your customer wants to take advantage of capacity planning in portfolios. The customer would like to use generic resources, because they have greater flexibility to respond to changing costs by resource by location. In fact, they would prefer not to set up any roles at all in the database, because they perceive generic resources and roles to be duplicate effort. What would an appropriate response be to this customer?

  • A. Use generic resources in Capacity Planning view, because they have greater ability to respond to changing costs.
  • B. User generic resources for project financials, and mirrored roles for capacity planning.
  • C. Use roles for planning and project financials to eliminate duplicate data maintenance.
  • D. Integrate with HR systems to obtain automated generic resource pricing updates.

Answer: B

NEW QUESTION 6
Identify one new feature in Release 8 related to Resource Management.

  • A. Resource GANTT chart
  • B. Resource capacity versus demand
  • C. Resource teams
  • D. Role teams

Answer: A

Explanation:
New features include a resourceGantt chart and the definition of rolling date windows saved to views.

NEW QUESTION 7
In your project, cost and work effort is not subject to change. Which duration type should be used?

  • A. Fixed Units
  • B. Fixed Duration and Units/Time
  • C. Fixed Units/Time
  • D. Fixed Duration and Units

Answer: A

Explanation:
Cost and work is here least flexible. If total work effort or fixed costs are most important, choose Fixed Units.
Note: Working with Duration Types Duration type options
Duration type determines whether the schedule, resource availability, or cost is most inflexible when calculations are performed to reflect activity progress. Duration type affects update calculations only when resources are assigned to an activity.
Choose a duration type based on which factor is the most important, or least flexible, in planning your project.
If schedule is most important, choose Fixed Duration and Units/Time or Fixed Duration and Units.
If resource availability is most important, choose Fixed Units/Time.
If total work effort or fixed costs are most important, choose Fixed Units.

NEW QUESTION 8
You are an executive that wants to review portfolio data for a high-risk/high-priority group of projects. You go to Portfolios in Primavera P6 Web. However, the data shown is not the correct portfolio. What should you do to correct this problem?

  • A. Manage the desired portfolio.
  • B. Open the desired portfolio.
  • C. Filter the portfolio in a dashboard.
  • D. Create a user portfolio view.

Answer: C

NEW QUESTION 9
Identify the true statement regarding Activity Step templates.

  • A. Activity % complete must be Physical when using Activity Step templates.
  • B. There are limits to the number of Activity Step templates in the database.
  • C. Activity Step templates are the place where resources are allocated and assigned.
  • D. Activity Step Templates are governed by global security.

Answer: A

Explanation:
Requirements for using weighted steps to calculate Activity Percent Complete
All of the following must be in place
* The Percent Complete Type for the activity that is using weighted steps must be set to Physical.
* In the Project Management module, a project-level option must be turned on.
* Weight values must be specified and work progress must be reported for each step.
Note: Activity Step Templates – to define sets of reusable steps common to many activities in a project or across projects.
Reference: Oracle Primavera P6, Activity Steps Overview

NEW QUESTION 10
Identify one filter enhancement in P6 R8.

  • A. Apply multiple filters simultaneously
  • B. Create filters with no more than three criteria
  • C. Cut, Copy, and paste filters
  • D. Assign filters to unique, single activity views

Answer: D

Explanation:
New in Release 8.2 include:
* Is Under filter: This is a new property used in filtering data which lets you filter by location of an item within a hierarchy. For example, you can filter for activities only under a certain WBS (Work Breakdown Structure) node. See figure below:
1Z0-567 dumps exhibit

NEW QUESTION 11
The two global profiles that are hard-coded in the system and cannot be deleted or changed ____ and ____.

  • A. Project Manager
  • B. System Administrator
  • C. IT Administrator
  • D. Admin Super User
  • E. Resource Manager
  • F. No Global Privileges

Answer: DF

Explanation:
In addition to any global profiles that you define, P6 provides two predefined global profiles: Admin Superuser and No Global Privileges.
Reference: Application Level Security

NEW QUESTION 12
Where are risk response plans captured?

  • A. In the Risk Scoring Matrix
  • B. In the Activity Notebook for Risk
  • C. In the Risk Register
  • D. In the Project Notebook for Risk

Answer: C

Explanation:
The Response Plans detail window is the area in the risk register where you create plans for handling the identified risks. Once you have identified which project risks need further action, create a response plan and assign response plan action items for each risk to reduce the negative impact on the project.
Example below:
1Z0-567 dumps exhibit
Reference: Oracle Primavera P6, Working with Risk Response Plans

NEW QUESTION 13
Calculated project user-defined fields _____ and ______.

  • A. are created by system administrators
  • B. are managed by Configuration Management
  • C. are associated with formulas
  • D. are viewable in either the web interface or client
  • E. are defined in the web interface and only viewable in the web interface

Answer: CE

Explanation:
C: The Oracle Primavera EPPM Web Access product contains a functionality where by users can create their own calculated values and dashboard indicators for monitoring project KPI’s.
This is achieved by creating Project Calculated User Defined Fields. The formulas which can be populated in these fields is similar to a formula used in some spreadsheet applications e.g. Microsoft Excel.
Providing a simple and effective platform for creating all manner of organisation bespoke project
indicators.
1Z0-567 dumps exhibit
Note: User-defined fields enable you to customize fields and values and add them to the project database.

NEW QUESTION 14
Identify this icon:
1Z0-567 dumps exhibit

  • A. Customize Columns in the View
  • B. Customize Tabs in the Details
  • C. Customize GANTT Chart Options
  • D. Customize and Save View

Answer: C

Explanation:
See 3) below for the use of the Gantt Chart Options button.
1Z0-567 dumps exhibit
Customizing the Resources Assignments Gantt Chart Bars
Customize the settings for the Gantt chart view on the Resources Assignments page. You can set features for up to three bars per assignment.
To customize the resource assignments Gantt chart bars:
1) Click Resources.
2) On the Resources navigation bar, click Assignments.
3) On the Assignments page, click View and choose:
1Z0-567 dumps exhibit
Gantt Chart Options.

NEW QUESTION 15
What is the significance of setting "Summarize project based on high-level resource planning"?

  • A. Summarized project data will reflect top-down plans.
  • B. Summarized project data will reflect bottoms-up plans.
  • C. Summarized project data will reflect actuals pushed from another application.
  • D. Summarized project data will be monetized.

Answer: A

Explanation:
Typically, use the High Level Resource Planning option for future projects that are currently planning only high-level resource allocation requirements, or for projects that are underway, but for which you do not want to assign resources at a detailed activity- level.
Note: ‘Summarize Project Based on’ determines whether the Summarizer calculates and displays rolled-up data based on resource assignments at the activity or project level.
Note 2: You can summarize project data to a specific WBS level when calculating and maintaining summary data.
1Z0-567 dumps exhibit

NEW QUESTION 16
You received an e-mail from a portfolio manager asking you to check performance metrics for the past months on each of the projects filtered for that portfolio.
You cannot locate the portfolio that the email references. What is the probable cause?

  • A. It is a user portfolio created by the portfolio manager.
  • B. It is a user-filtered portfolio that has not been refreshed.
  • C. You do not have the appropriate license for the web interface.
  • D. You have not been assigned as a resource to the projects.

Answer: B

NEW QUESTION 17
All commands executed by toolbar icons can be accessed from three menus. Select the three menus.

  • A. Action
  • B. Copy
  • C. Edit
  • D. Paste
  • E. View
  • F. Remove
  • G. Modify

Answer: ACE

Explanation:
A:
Note: To facilitate a streamlined, role-specific configuration of P6 Web Access, your administrator can assign you to a user interface view that corresponds to your role and work processes in your organization. The tabs, tab icons, and action menu items that you can access in each section of P6 Web Access, and the order in which they appear, depend on your user interface view settings
C: The Edit menu is a standard Windows menu that lets you do common actions such as cut, copy, and paste.
E: The View menu is quite extensive, and the items available vary as you view different modules.
Note:
When you log into P6 the first time, you should be presented with a screen similar to the following screenshot:
1Z0-567 dumps exhibit

NEW QUESTION 18
Select the true statement regarding currencies.

  • A. Only one base currency is supported per database.
  • B. Currencies are updated daily per exchange rates.
  • C. Only 10 currencies are supported in Primavera.
  • D. Only two currencies are supported in Primavera.

Answer: A

Explanation:
The base currency is the monetary unit used to store cost data for all projects in the database and is controlled by a global administrative
setting in the Project Management module. The default base currency for Primavera is US dollars ($). The view currency is the monetary unit used to display cost data in Primavera and is controlled by a user preference.
Note: All costs are stored in the Based Currency. All costs are stored in the Base Currency and all other Currencies are calculated values using the Base Currency value and conversion rate.

NEW QUESTION 19
You are an application administrator that has been asked to create a portfolio for an executive. You create the portfolio and have the user test to see whether it meets requirements. However there are a couple of projects that are missing. You look for the portfolio, but it is no longer visible to you. What is the cause of this problem?

  • A. The global filters for the portfolio must be refreshed.
  • B. You do not have read/write access to the portfolio.
  • C. You created it for one user, and you are not that user.
  • D. The projects were deleted in error.

Answer: C

NEW QUESTION 20
The Open Requests for Resource's portlet lists unstaffed assignments involving roles on the selected role team. Identify two ways that the portlet display can be organized.

  • A. Role by Project
  • B. Role by Resource
  • C. Project by Role
  • D. Resource by Project
  • E. Resource by Role

Answer: AC

Explanation:
This portlet has a number of customizations. The first choice to be made is to show
open assignments on all projects or just those within the filter for this dashboard. The Organize field allows a user to define how the listed open assignments are sorted and shown. The drop-down list offers views where open assignments are shown as:
* Roles with open assignments project by project (A)
* Projects with open assignments role by role (C)
* Roles with open assignments, sorted by project, and sub-sorted by project codes
See figure below:
1Z0-567 dumps exhibit
Note: The Open Requests for Resources portlet allows users to show which activities on projects have only a role (that is, engineer) assigned and need a resource (that is, David Jackson) assigned by their Manager.
Note 2: A variety of pre-defined portlets come with P6.

NEW QUESTION 21
You are in a governance organization that has established a project management methodology with work product and document requirements that must be included in every project. You want to create s global activity view that includes a filter to show only activities that have required work products and documents as per the methodology. Identify three actions that would help you to accomplish this.

  • A. Create a Secure Global Activity Code.
  • B. Create a Global Security Privilege for the Governance organization.
  • C. Create a Global Governance Activity view.
  • D. Group and sort by Governance deliverable.
  • E. Create a filter available to the Governance organization.
  • F. Create a custom portlet for a Governance dashboard.

Answer: ACE

Explanation:
Filter on the Global Activity Code and display in the activity view.

NEW QUESTION 22
When is "Store Period Performance" usually performed?

  • A. After each pay period
  • B. After the schedule is updated
  • C. After Job Services validation
  • D. After working hours to enhance performance

Answer: A

Explanation:
Storing of Period Performance
When billing in Excel (AIA form) or in the P6 schedule the current billing period amounts must be “rolled” or moved to the Previously Billed or Actual Cost categories before starting a new billing period.
When the billing has been approved and finalized in the AIA form it can be copied to a new file for use in the next billing period. To “roll” or clear out the This Period amounts in Excel, the current period amounts will have to be added into the Previous Application column cells. This creates a starting point for the new billing period.
Note:
In P6, by default, actuals will be distributed evenly across time periods. For example, we set up an activity to start the first day of May, and we have actuals for the month of May of 15 hours. We have actuals for the month of June of 25 hours. P6 will display this as 20 hours for May and 20 hours for June. To get the exact amount of hours for each month, you have to store period performance. To do this, take the following steps:
1.) Set up your financial periods:
Select Admin, Financial Periods from the Menu Bar
You can either add your financial periods manually, or set up a batch run by entering the start date and end date and how often the period should be created.
2.) Enter your actuals for the resource into the column, Actuals This Period. It will also put the same amount in the Actual Units Column; at the end of May, Actuals This Period would have 15 hours, as would Actual Units.
3.) When you are done with the update, do Tools, Store Period Performance. This will move the Actuals this Period to the appropriate financial period and zero out the Actuals This Period column. At the end of June, enter 25 hours in Actual This Period. Actuals This
Period will have 25 hours and Actual Units will have 40 hours. 4.) To view the financial periods, do the following:
Click Edit, User Preferences Click on the Application Tab
Enter the Financial Periods that you would like to view.
In the Activity Window, add the financial period columns (they will start with the financial period).

NEW QUESTION 23
......