Examcollection offers free demo for 200-601 exam. "Managing Industrial Networking for Manufacturing with Cisco Technologies", also known as 200-601 exam, is a Cisco Certification. This set of posts, Passing the Cisco 200-601 exam, will help you answer those questions. The 200-601 Questions & Answers covers all the knowledge points of the real exam. 100% real Cisco 200-601 exams and revised by experts!
2026 New 200-601 Exam Dumps with PDF and VCE Free: https://www.2passeasy.com/dumps/200-601/
Q1. Given the CIA triad elements, which ensures first that the data is encrypted and secure, second that the data is trustworthy, and third that the data is accessible by those who need it?
A. CIA
B. ICA
C. ACI
D. CAI
Answer: A
Q2. What security component can be deployed to increase the defense in depth and specifically can be positioned against 'man-in-the-middle' attack?
A. Deploy 802.1AE
B. Deploy 802.1X
C. Deploy 802.1Q
D. Deploy 802.1AX
Answer: A
Q3. Refer to the exhibit.
All of the vlans listed in the routing table below are trunked using 802.1q and are active on all switches. PLC1, PLC2, and PLC3 each has IP address 192.168.0.1/24 and are connected to ports configured for vlan 50. L2SW1, L2SW2, and L2SW3 are not using vlan trunking for vlan 50.
L3SW1 has following routing table:
10.0.0.0/8 is variably subnetted, 12 subnets, 2 masks C.10.3.138.0/23 is directly connected, Vlan307 C.10.3.136.0/23 is directly connected, Vlan306 C.10.15.153.0/24 is directly connected, Vlan398 C.10.3.142.0/23 is directly connected, Vlan309 C.10.3.140.0/23 is directly connected, Vlan308 C.10.3.186.0/23 is directly connected, Vlan293 C.10.15.154.0/24 is directly connected, Vlan399 C.10.3.184.0/23 is directly connected, Vlan292 C.10.3.190.0/23 is directly connected, Vlan295 C.10.3.188.0/23 is directly connected, Vlan294
C.10.3.182.0/23 is directly connected, Vlan291
C.10.3.180.0/23 is directly connected, Vlan290
PLC1, PLC2, and PLC3 cannot be reconfigured. What can be done to be able to simultaneously communicate with PLC1, PLC2, and PLC3?
A. Enable NAT on L3SW1
B. Enable NAT on L2SW1 – L2SW3
C. Enable NAT on L2SW4
D. Add vlan 50 to L2SW4 and assign.the administrator's.an IP address on 192.168.0.0/24 network
Answer: B
Q4. You are making changes to a Stratix 5700 using an Add On Profile (AOP) and a controller which is on-line with RSLogix5000. When do the changes you have made get published to the switch?
A. While online in RSLogix 5000 software the changes made in the AOP are pushed to the switch after pressing the Set button.
B. All of the changes are automatically pushed to the switch.
C. Changes to the AOP can only be made from the switch, not in RSLogix 5000.
D. RSLogix 5000 will push the changes in the AOP to the Stratix 5700 when you right click on the switch, and choose download to switch
Answer: A
Q5. A ProfiNET management system operator is unable to see diagnostic information for a Cisco Industrial Ethernet switch that has been added to a SIMATIC management station. Based on the provided CLI output, which statement is correct?
switch# show profinet status
State.: Enabled
Vlan.: 201
Id.: IE2000-Switch
Connected : Yes
ReductRatio : 128
GSD version : Mis-match
A. The assigned ProfiNET VLAN is not valid and should be less than 100
B. LLDP has been disabled on this switch
C. The GSD file version on the switch does not match the GSD file version on the management station
D. The Reduction Ration has been set too low
Answer: C
Q6. A cookie cutter machine requires 2 standard controllers and a safety controller. All of these controllers and machine level I/O have been placed on VLAN 104. The safety controller must monitor an emergency stop connected to an I/O adapter on an adjacent machine (VLAN 105). Which packet type will be used?
A. UDP Multicast TTL = 1
B. UDP Multicast TTL = 2
C. UDP Unicast
D. TCP Unicast
Answer: C
Q7. Which in-depth approach is used when deploying defense in an industrial zone?
A. Besides using a dedicated firewall / DMZ construction use an IOS based firewall on the WAN router connecting the industrial site to the Internet.
B. Use NTP to make sure that time stamps of log messages are synchronized such that you can do root cause analysis.
C. Deploy an IDS solution with knowledge about industrial protocols in the industrial zone in combination with a firewall.
D. Use multiple firewalls from different vendors in such a way that network traffic will have to traverse both firewalls so that security holes of one firewall is caught by the other firewall.
Answer: C
Q8. To correctly integrate a Cisco Industrial Ethernet switch into a ProfiNET management system such as SIMATIC STEP 7 or TIA Portal, which is a mandatory action?
A. Configure an IP address on the ProfiNET VLAN interface
B. The General Station Description (GSD) file must be uploaded from the switch to the management system.
C. Enable Quality of Service (QoS) and ensure the management station interface is trusted
D. Enable SNMP on the switch
Answer: B
Q9. Which configuration enables an Industrial Ethernet switch to participate in PTP clock selection and sets the priority value that would break the tie between switches with matching default criteria to 50?
A. ptp mode boundary ptp priority1 10 ptp priority2 50
B. ptp mode boundary ptp priority1 50 ptp priority2 10
C. ptp mode e2etransparent ptp priority1 50 ptp priority2 10
D. ptp mode e2etransparent ptp priority1 10 ptp priority2 50
Answer: A
Q10. Profinet has been disabled on a Cisco Industrial Ethernet switch, which.CLI commands correctly enable ProfiNET on VLAN 10?
A. switch(config)#profinet switch(config)#profinet vlan 10
B. switch#enable profinet switch(config)#profinet vlan 10
C. switch(config)#profinet switch(config)#vlan 10 switch(config-vlan)#profinet
D. switch#enable profinet switch(config)#vlan 10 switch(config-vlan)#profinet
Answer: A