Certleader offers free demo for PMP exam. "Project Management Professional", also known as PMP exam, is a PMP Certification. This set of posts, Passing the PMP PMP exam, will help you answer those questions. The PMP Questions & Answers covers all the knowledge points of the real exam. 100% real PMP PMP exams and revised by experts!
Free demo questions for PMP PMP Exam Dumps Below:
NEW QUESTION 1
The Administer Procurements process is in which of the following Project Management Process Groups?
- A. Planning
- B. Monitoring and Controlling
- C. Initiating
- D. Executing
Answer: B
NEW QUESTION 2
Using the following data, what is the Schedule Performance Index (SPI)? EV= $500 PV= $750 AC= $1000 BAC= $1200
- A. 0.67
- B. 1.5
- C. 0.75
- D. 0.5
Answer: A
NEW QUESTION 3
Which degree of authority does a project manager have on a project in a strong matrix organizational structure?
- A. Limited
- B. Low to moderate
- C. Moderate to high
- D. High to almost total
Answer: C
NEW QUESTION 4
What is project management?
- A. A logical grouping of project management inputs, outputs, tools, and techniques
- B. Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements
- C. Launching a process that can result in the authorization of a new project
- D. A formal, approved document that defines how the project is executed, monitored, and controlled
Answer: B
NEW QUESTION 5
The total of the planned value (PV) is also known as:
- A. work breakdown structure (WBS).
- B. schedule target.
- C. performance measurement baseline (PMB).
- D. earned value baseline.
Answer: C
NEW QUESTION 6
In a weak matrix, the project managers role is:
- A. part-time
- B. full-time
- C. occasional
- D. unlimited
Answer: A
NEW QUESTION 7
When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
- A. event.
- B. response,
- C. perception.
- D. impact.
Answer: A
NEW QUESTION 8
The cost benefit analysis tool is used for creating:
- A. Pareto charts.
- B. quality metrics.
- C. change requests,
- D. Ishikawa diagrams.
Answer: B
NEW QUESTION 9
Which of the following is a project constraint?
- A. Twenty-five percent staff turnover is expected.
- B. The technology to be used is cutting-edge.
- C. Project leadership may change due to volatile political environment.
- D. The product is needed in 250 days.
Answer: D
NEW QUESTION 10
Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?
- A. Project Time Management
- B. Project Cost Management
- C. Project Scope Management
- D. Project Human Resource Management
Answer: A
NEW QUESTION 11
When is a project finished?
- A. After verbal acceptance of the customer or sponsor
- B. After lessons learned have been documented in contract closure
- C. When the project objectives have been met
- D. After resources have been released
Answer: C
NEW QUESTION 12
Work performance information and cost forecasts are outputs of which Project Cost Management process?
- A. Estimate Costs
- B. Plan Cost Management
- C. Determine Budget
- D. Control Costs
Answer: D
NEW QUESTION 13
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
- A. Project management plan.
- B. Project charter.
- C. Work breakdown structure.
- D. Stakeholder register.
Answer: B
NEW QUESTION 14
The product scope description is used to:
- A. Gain stakeholders support for the project.
- B. Document the characteristics of the product.
- C. Describe the project in great detail.
- D. Formally authorize the project.
Answer: B
NEW QUESTION 15
Inputs to Identifying Stakeholders include:
- A. Project charter, procurement documents, enterprise environmental factors, and organizational process assets.
- B. Project charter, stakeholder analysis, enterprise environmental factors, and organizational process assets.
- C. Project charter, stakeholder analysis, enterprise environmental factors, and stakeholder management strategy.
- D. Project charter, procurement documents, expert judgment, and organizational process assets.
Answer: A
NEW QUESTION 16
The run chart created during the Perform Quality Control process on a project is used to show the:
- A. relationship between two variables
- B. data points plotted in the order in which they occur
- C. most common cause of problems in a process
- D. frequency of occurrence
Answer: B
NEW QUESTION 17
Which tool or technique is an examination of industry and specific vendor capabilities?
- A. Independent estimates
- B. Market research
- C. Analytical techniques
- D. Bidder conferences
Answer: B
NEW QUESTION 18
The scope management plan and scope baseline are contained in:
- A. organizational process assets
- B. a requirements traceability matrix
- C. the project charter
- D. the project management plan
Answer: D
NEW QUESTION 19
What is a tool and technique used in the Develop Project Management Plan process?
- A. Project management information system (PMIS)
- B. Project charter
- C. Quality assurance
- D. Expert judgment
Answer: D
NEW QUESTION 20
A tool and technique used during the Collect Requirements process is:
- A. prototypes.
- B. expert judgment.
- C. alternatives identification.
- D. product analysis.
Answer: A
NEW QUESTION 21
Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?
- A. Initiating
- B. Planning
- C. Executing
- D. Closing
Answer: C
NEW QUESTION 22
......